Our Projects Elk Falls Water Quality Treatment Plant (EFWQTP) Abandonment Project

Client

City of Campbell River

Engineer

Highland Engineering Services Ltd

Scope

The abandonment of all civil infrastructure inside and outside of the UV Treatment Building and reinstatement of all disturbed areas.

Summary

Work under this contract needed to be carefully detailed, planned and executed using the highest of safety standards. A large portion of the the pipe to be removed and disposed of was either AC Pipe or Steel Pipe with AC coating or lining and ranged in size from 250mm Ø to 1050mm Ø. The remaining infrastructure was abandoned and filled with a total of 340 cubic meters of CDF Concrete. Completion of this project included the reinstatement of the concrete floor within the UV Building, final grading and Hydroseeding.